ResearchProfessional PracticePlanning Documents for Landscape Projects

Planning documents for landscape projects

What a brief, work breakdown, responsibility matrix, schedule basis and kickoff agenda should contain, from public owners' templates, adapted to landscape work.

Field Method · AI-assisted research roundupPublished Sources checked

A project folder can hold a brief, a task list, a role chart, a bar chart and meeting minutes, and the team can still disagree about what is included. We propose that each of the five planning documents settle a different question and that all of them use one numbered list of deliverables.

This article reads what public owners publish for each document. It then proposes a landscape version. That version is our own, and we have not tested it on a project. Few of the sources were written for a small design office.

What each document settles

Document Question it settles Who should agree to it (our suggestion)
Brief or charter What is the project, what is outside it, and who can decide? Client and design lead
Work breakdown What will be delivered, and where does each piece stop? Design lead and each discipline
Responsibility matrix Who makes, approves and advises on each deliverable? Everyone named in it
Schedule and its basis When, and on what assumptions? Client and design lead
Kickoff agenda Does everyone read the first four the same way? The meeting, through its minutes

The brief or charter

A program describes the place. A charter authorizes the work. We think a landscape brief needs both.

The National Park Service gives a full public example of the first. Its Denver Service Center defines the project program as a site analysis, a site program and an architectural program, and says the architectural program may not be required where there is no building or structure. NPS definitions, P, updated October 8, 2026 The site program is a narrative list of functions that says which to include or exclude and how they relate, with bubble diagrams. The site analysis covers slope, access, vegetation, water, utilities, soils, hydrology, site history and existing hazardous materials, and the source of each item is identified. NPS definitions, S, updated August 11, 2026

California’s Department of Technology publishes an example of the second. Its charter template asks for measurable objectives with assessment criteria, an in-scope and out-of-scope table, roles, assumptions, constraints, early risks, milestones, rough budget, funding sources, governance and dependencies on other projects. It asks who approves funding, who approves work products, and who signs off on progress, changes and completion. CA-PMF Project Charter template The template is for state technology projects.

The template also makes the author rank time, cost and scope as cannot change, could be changed or can be improved, with one mark in each row and column.

GSA does not require a charter on every project. Its March 2026 order says the project sponsor starts the charter with the project manager, and points to an intake guide and a tools matrix for charter requirements. When a charter is created, the project manager must start a project management plan. Projects that meet the intake guide’s criteria must also have a plan. It must be revised and resubmitted when the project manager changes, or when scope, schedule, budget or the impact on quality changes significantly. GSA Order PBS 3425.12C, March 24, 2026

Our landscape brief, on two pages.

  • Purpose, and the test that will show it was met.
  • Limit of work on a dated base, with adjoining work by others named.
  • Included and excluded services: survey, arborist, soils, irrigation audit, permits, public meetings, construction visits, establishment visits.
  • Site facts with their sources, and the facts still missing.
  • Time, cost and scope ranked.
  • Deliverable list, numbered as in the work breakdown.
  • Decisions, with who makes each one and the latest useful date, as in our stakeholder article.
  • Who will maintain the site, and what they can maintain.
  • Budget basis. Our cost planning article covers estimate classes and change records.

Write the decision line with care. The City of San Diego says a General Development Plan must be approved before park improvements are made. For a new plan or an amendment, it describes at least two meetings with a Community Recreation Group and at least one with the Parks and Recreation Board. Each body votes on a recommendation, and final department approval follows. The page gives exceptions. Minor projects that need no amendment are presented to the group and then proceed. The Board may recommend minor amendments without a public meeting. Another advisory body may host where there is no group in good standing. San Diego Park Design FAQ A brief that says “City approval” would hide which route applies. Confirm it with the City.

We suggest that the brief restate the signed scope, cite its exhibit and say that the signed agreement governs. Send any item found missing at kickoff to the client as a change request before work on it starts.

The work breakdown

GAO calls a product-oriented work breakdown structure a best practice because cost and schedule can be tracked by defined deliverables. It says the second or third level should be products. Design engineering, quality assurance and meetings are among its examples of non-products. It also says every structure includes program management at level two, with other common elements. GAO-20-195G, March 2020 GAO writes for large federal programs.

The Caltrans guide describes a structure by deliverable, yet its fourth level is the project phase. Each work package should be assignable to one person or unit, the lead function. Caltrans Workplan Standards Guide, Release 15.0, effective March 1, 2025

The guide includes these landscape elements, among others. Planting design concepts are 160.10.30. The draft plans stage has planting plans (230.10.05), plant list (230.10.15), irrigation plans (230.10.20) and irrigation quantity sheets (230.10.30). Planting specifications are 230.35.10, and quantities and estimates are 230.40.10. Landscape architecture is the lead function for each, shown as “Landscape Architect” for irrigation plans. All four of those draft-plan elements name the same deliverable, final highway planting plan sheets. Caltrans Workplan Standards Guide Our reading is that such codes are too coarse to show when the irrigation plan is done.

Our scheduling article breaks work down by phase and lists the external dependencies of each. To control scope we propose a second view: components at level two, documents at level three, and phase as a code on each document. Soils then stay one element from report to specification.

An example for a small plaza, invented for illustration:

  • 1 Site information: survey, tree report, utility records
  • 2 Grading and drainage: plan, spot elevations, coordination with the civil engineer
  • 3 Paving and site elements: layout, details, finish samples
  • 4 Soils and planting: soil report, soil specification, tree plan, plant schedule, establishment notes
  • 5 Irrigation: water calculation, plan, controller notes
  • 6 Whole project: permit application, estimate, remaining specifications, public meetings
  • 7 Management and support: coordination, quality review, bid support, construction and establishment visits

Element 6 holds work that belongs to no single component. GAO’s guidance would spread meetings into the elements they serve. We keep public meetings as an element because, in our example, they end in a deliverable: a presentation and a record.

We rely most on the dictionary. GAO’s schedule guide says the dictionary defines the scope of each element, and that activities without an element reflect undefined scope. GAO-16-89G, December 2015 California’s template asks for number, task, description, work products and owner. CA-PMF WBS template We add four fields: starts when, stops where, excluded, accepted by (internal acceptance). For the tree plan, 4.3: “Starts when the utility records are in. Stops at the tree grate frame, which is in 3. Excludes the arborist’s report, which is in 1. Accepted by the landscape architect.” The stopping point is where landscape teams meet civil, structural and electrical teams.

The responsibility matrix

California’s matrix has deliverables down the side, starting with those in the work breakdown, and people across the top. Its letters are responsible, accountable, consulted, informed and a fifth, sign, for a formal show of support or dissent. It says every deliverable should have at least one resource creating it and one approving it. A blank means no role. CA-PMF RACI Matrix template

Other points from the sources:

  • Membership. Caltrans names a minimum project team that includes surveys, construction and maintenance. It says the district or project landscape architect should be a member on all projects that involve or affect planting, access and safe working conditions for vegetation management, roadside rest areas, noise barriers and scenic highways, and should be offered a place on other types. Caltrans PDPM Chapter 8, November 6, 2024 GSA’s plan must list internal and external people with roles and contact details, and officials of contributing offices and the customer agencies must affirm it. GSA Order PBS 3425.12C
  • Inputs. Washington State DOT’s agreement with a support group records the scope, deliverable dates, predecessors, risks, and what the group needs first, who supplies it and when. WSDOT Internal Scope-of-Work Agreement

Our rules. Use one A per row, held by a named person, for internal acceptance. The California template allows more than one; we think a shared approval is hard to close. Give agency approval its own column. Add a column for “needs first, from whom”. Limit the rows to things that get issued. Our quality control article covers who reviews each issue.

Deliverable (example) R A C I Agency approval Needs first, from whom
4.3 Tree plan Landscape designer Landscape architect Civil, lighting, arborist Client City forester, if required 1.3 Utility records, civil
4.2 Soil specification Landscape architect Principal Soil scientist Civil None assumed 4.1 Soil report, client’s consultant
5.2 Irrigation plan Irrigation designer Landscape architect Maintenance staff Client Water agency, if required Water pressure, water agency
2.2 Spot elevations Civil engineer Civil engineer Landscape architect Client None assumed 1.1 Survey, client’s surveyor

Roles stand in for names here. Numbers follow the order of the list above. The last row shows one person making and accepting, so it needs a separate quality review. The matrix does not answer who must be in responsible charge of a drawing. Ask the licensing board.

The schedule and its basis

A bar chart shows dates. A basis document explains them. GAO’s minimum contents include a program description, execution strategy, schedule structure, software settings, ground rules, assumptions and exclusions, a reason for each lag and date constraint, calendars and workday exceptions, the approach to key durations, resources, critical path and float, main risks and contingency, and the update and change process. GAO treats it as a living document. Each activity should also trace to a work breakdown element and have an owner. GAO-16-89G

Our one-page basis for a landscape project:

  • What the schedule covers, and where it stops: bid, acceptance, or the end of establishment.
  • Working calendar, holidays, and the client’s review calendar.
  • The deliverable number on each activity line.
  • For each external duration in the schedule: source, date read, and whether published, quoted to us or assumed.
  • Planting window, set by whom and from what.
  • Review loops, as a count and a length.
  • Every fixed date, with its reason.
  • What is excluded, such as appeals or bid protests.
  • Who may change the baseline, and how the change is recorded.

In the City of San Diego’s as-needed landscape architecture agreement, each task order must include a scope, a cost estimate and a time for completion. The form gives the time sequence one completion date and a reference to the scope. San Diego Contract H2526693-M Our reading is that the form leaves interim dates and assumptions to the attached scope, so a consultant can add a basis page there if the City agrees.

The kickoff agenda

Kentucky’s local project guide requires a team kickoff for every project after a design professional is selected, and recommends holding it after funds, agreement and consultant are in place and before design begins. The minimum topics are scope, budget and schedule, deliverables, right-of-way, utility and environmental impacts, environmental document and who prepares it, design standards, permits, railroad involvement and further meetings. The local agency or consultant is asked to bring a completed draft of scope and responsibilities, and to write formal minutes. KYTC LPA Guide Chapter II, December 18, 2025

Washington State DOT’s agenda assigns most topics to an office or group, asks whether scope agreements have gone out, asks what is expected at each milestone, and ends with actions by what, who and when. WSDOT Kick-off Meeting Template

Our agenda, 90 minutes, drafts sent a week before:

  1. Boundary: read the included and excluded lists aloud, then ask each discipline for one missing item (20 minutes).
  2. Site facts: what is missing, who gets it, by when (15).
  3. Interfaces: walk the numbered deliverables and the stopping points between disciplines on a plan (20).
  4. Matrix: each person confirms their own rows (10).
  5. Schedule basis: challenge the assumptions before the dates (15).
  6. Decisions, actions, next meeting (10).

The order, the times and the week’s notice are ours and untested. We suggest inviting maintenance staff and the client’s planting reviewer to items 1 to 3. Meet agency reviewers separately if needed.

How much is enough

For a small project we would keep the brief, a deliverable list with stopping points, and the basis page, and put the R and A letters on the list. We propose two checks. Pick any deliverable and follow its number through the brief, breakdown, matrix, schedule and kickoff minutes; record each break. Then ask a person who missed the kickoff to say, from the documents alone, what is excluded and who decides next; record each wrong answer. Neither check has been run.

What we could not settle

  • Does this set reduce rework on landscape projects? We did not search for studies or test it.
  • What does the City of San Diego’s 2024 Park Design Manual say about program meetings, schedules and consultant roles? The file was too large for our reader.
  • What does NASA’s 2025 work breakdown handbook say? It did not open, so we did not use the 2021 edition.
  • What does GSA’s intake guide require of a charter?
  • Which roles on a landscape drawing must match a licensed person in a given state? Ask the licensing board.
  • What do the Project Management Institute’s standards say? We did not open them.

Using this in Field Method

Site Lens collects public site data for San Diego County in one study, with terrain and tree records. It can support the site facts line of a brief. It is not a survey, and it does not write briefs, matrices or schedules.

Sources

  1. National Park Service, Denver Service Center Workflows — Definitions P (Predesign, Project Program, Project Management Plan)
  2. National Park Service, Denver Service Center Workflows — Definitions S (Site Analysis, Site Program)
  3. California Department of Technology, CA-PMF — Project Charter Template with Instructions
  4. GSA Order PBS 3425.12C — Project Management in the Public Buildings Service
  5. City of San Diego Parks and Recreation — Park Design FAQ
  6. GAO-20-195G — Cost Estimating and Assessment Guide: Best Practices for Developing and Managing Program Costs
  7. Caltrans — Workplan Standards Guide, Release 15.0
  8. GAO-16-89G — Schedule Assessment Guide: Best Practices for Project Schedules
  9. California Department of Technology, CA-PMF — Work Breakdown Structure Template with Instructions
  10. California Department of Technology, CA-PMF — RACI Matrix Template with Instructions
  11. Caltrans — Project Development Procedures Manual, Chapter 8: Overview of Project Development
  12. Washington State DOT — Internal Scope-of-Work Agreement
  13. City of San Diego — Agreement for As-Needed Landscape Architectural Services, Contract H2526693-M
  14. Kentucky Transportation Cabinet — LPA Guide, Chapter II: Initial Project Team Meetings
  15. Washington State DOT — Kick-off Meeting Template