ResearchProfessional PracticeProject Planning and Scheduling Techniques

Planning and scheduling landscape projects

A phase breakdown from site analysis to establishment, and what public sources say about review cycles, utility notice, planting season and plant lead times.

Field Method · AI-assisted research roundupPublished Sources checked

A landscape project schedule has two kinds of durations. Some are work the office controls. Others belong to someone else: a plan-check queue, a utility locate, a nursery, a growing season. Our interpretation is that on projects with agency review, public bidding or contract-grown plants, the second kind often sets the finish date. We suggest fixing those dates first.

This article proposes a work breakdown for planning, which is ours and untested. It then reads what public agencies publish about the external durations, each number with its jurisdiction.

A work breakdown by phase

By work breakdown we mean a list of a project’s deliverables in a hierarchy, so that every task belongs to one deliverable. That is our working definition, and the breakdown below is our own. We could not open the Project Management Institute’s standard on the subject.

Phase Typical work packages External dependency to schedule
Site analysis Base data, survey request, site visit, constraints map Survey and geotechnical vendors, record requests
Concept and schematic design Program, options, client review, cost range Owner review, public meetings
Discretionary review and environmental clearance, where required Application, environmental documents, responses Completeness review, review cycles, lead agency determination, hearings
Design development Grading, planting and irrigation concepts, utility coordination Utility owners
Construction documents and plan check Plans, specifications, calculations, submittal, comment responses, resubmittal Review cycles on ministerial permits, plant availability
Bid and award Addenda, bid review, award Advertising period, protests
Construction administration Submittal review, site visits, field reports Contractor submittals, utility locates, planting season
Establishment and close-out Punch list, irrigation audit where required, establishment inspections, acceptance Establishment period, final approvals

The table assumes a publicly bid, design-bid-build project. On a private commission the bid row may be a negotiated price with no advertising period or protest. Who holds the construction schedule and the establishment work depends on the contract. Phases overlap. Where a discretionary permit is needed, we place that review on early drawings, before construction documents.

We suggest giving each external dependency its own line with a named owner, so that waiting time shows as its own duration.

How long one public owner says whole projects take

The City of San Diego’s Capital Improvements Program publishes high-level estimates, from initial funding to award of the construction contract, for four asset types. We list the park figures. They are written for residents, and the City says projects vary greatly. City of San Diego CIP guidance, September 1, 2024

  • Improvements to existing parks: about 2 years, assuming outreach is complete, no General Development Plan amendment, a consultant designer and design-bid-build delivery.
  • New parks: about 3 years, assuming an approved General Development Plan, which itself takes a minimum of 18 months.

As the City lists them, consultant design support, private utility relocations, its zero-emissions building policy and CEQA, NEPA or other permits add six months to 1 year. The existing-park figure already assumes a consultant. Some permits take over two years. Land or easement acquisition can add up to 2 years. Bid protests can delay the start of construction by six months or more. Design-bid-build advertise and award averages about 6 months.

These figures stop at contract award, before construction and establishment. They describe one city’s public program, run from initial funding and assume public bidding.

Agency review cycles

What the City of San Diego publishes. For discretionary development permits, the Land Development Manual says a completeness review can take up to 30 calendar days and averages 10 working days. San Diego Land Development Manual, Section 4, October 2024 The landscape section reviews building, grading and public improvement plans against the Landscape Standards and the Land Development Code. Its page states no timeline. San Diego, Landscape Plan Review

The City’s timeline page says its figures are weekly estimates that vary with volume and document completeness. Its permit issuance table, stamped as current on November 13, 2026, listed approximately 5 business days for grading, public improvement and mapping permits. That is an issuance time. The review table is an embedded report that the page says is in calendar days and reflects data from the day prior. On November 14, 2026 its standard-review tab listed eleven review disciplines. Average first reviews ranged from 6 to 28 calendar days and rechecks from 6 to 16, for example 16 and 15 days for planning review. The table has no landscape row, so we give no landscape plan-check duration. We did not open its express, expedite or rapid review tabs. San Diego, Permit Processing Timeline

What a state housing fact sheet says. The following comes from a fact sheet that the California Department of Housing and Community Development wrote for housing development. Whether it reaches a landscape-only permit is a question for the agency or counsel. The sheet summarizes the Permit Streamlining Act: a local jurisdiction has 30 calendar days to determine in writing whether a development project application is complete, and the application is deemed complete if written findings are not provided in that period. A final written determination on an appeal of an incompleteness determination is due within 60 calendar days. HCD, Permit Streamlining Act fact sheet, April 2026 We could not open the statute itself.

Environmental review. The CEQA Guidelines say the public review period for a draft environmental impact report (EIR) “shall not be less than 30 days” and that it should not be longer than 60 days except in unusual circumstances. The minimum is binding wording. The upper figure is advisory. When a draft EIR goes to the State Clearinghouse for state agency review, the period shall not be less than 45 days unless the Clearinghouse approves a shorter one of at least 30 days. 14 CCR § 15105, current through October 30, 2026 The state’s summary, published under the name of the Governor’s Office of Planning and Research, gives both figures as limits. OPR, CEQA 101 We read no other Guidelines section. Whether a project needs a document at all is for the lead agency.

Scheduling rule (ours). Treat every review as a loop with a count. Enter a first review, the response time and at least one recheck. Use the agency’s published figure where there is one and a stated assumption where there is not, and record which is which.

Utility coordination

Excavation carries a notice duty that the regional notification centers describe as the excavator’s. This is a legal and safety matter. The centers and Government Code section 4216 and following are the authority, and we could not open the statute.

For San Diego County the center is DigAlert, which says it serves nine Southern California counties including San Diego. Its page says excavators must give at least two working days’ notice before excavating, with the date of notification left out of the count. DigAlert, About Its FAQ page says anyone doing any type of digging must contact it, except homeowners working on their own property without a permit or powered equipment. It also says DigAlert handles planned excavation and does not handle pre-planning or design-stage planning, in answer to a question about starting digging within 14 days. DigAlert, FAQs We found no ticket-life figure on the DigAlert pages we read.

The Northern California edition of the USA North 811 field guide gives more detail for that center. It tells excavators to contact 811 at least 2 working days before digging, with the notification day left out of the count. Its Normal ticket is for excavation scheduled to begin 2 working days to 14 calendar days after the ticket is submitted. It says digging can begin only after all utility operators have given a positive response, and that work within 10 feet of a high priority line requires an on-site meeting first. It says tickets are active for 28 calendar days, that state law requires excavators to keep an active ticket for the whole excavation, and that a renewal extends a ticket. USA North 811 Field Guide, August 2026

Our interpretation, for scheduling only: both centers tie a ticket to work that starts soon, so the excavator’s locate request belongs close to the start of digging. Two working days is a minimum wait and can run longer. Design-stage utility coordination is a separate, earlier activity with the utility owners. Confirm the notice rules for a site with its regional center.

Planting season and plant availability

Season. We found no agency or extension source that gives a planting window by month for San Diego County. The University of California’s statewide integrated pest management program says container-grown woody plants can be transplanted at any time of year and that planting in fall through spring is ideal. UC IPM, Plant Properly That is a statewide statement with no months and no regional detail. Caltrans treats season as a schedule matter on its own contracts. Its Construction Manual tells resident engineers to consider delaying planting to a more favorable period when weather would kill or severely damage plants, and says nonworking days may be granted if the delayed planting is the controlling operation. Caltrans Construction Manual, Section 4-20, October 2023 We treat the planting date as an assumption that the specifier sets from the species and the site.

Lead time. California Botanic Garden’s restoration nursery says it does not keep large quantities in stock and grows all plants on a contract basis. It recommends contact one to two years before a project is set to commence, depending on container size. California Botanic Garden, Restoration Nursery This describes one native-plant restoration nursery. We found no primary source for ordinary landscape nursery stock.

Contract language. Caltrans shows how one owner writes plant dates into a contract. Its standards page gives October 19, 2026 as the implementation date of the 2026 edition. Caltrans, Standard Plans and Standard Specifications In that edition, the contractor submits a vendor statement that the plant order has been received and accepted at least 60 days before planting (section 20-3.01A(3)(b)), and notifies the Engineer at least 10 days before plants are shipped. Unsuitable new plants must be replaced within 2 weeks after the Engineer marks them (section 20-3.01C(4)). A separate clause covers existing plants that the contractor damages: they are replaced before an establishment period starts, or otherwise at least 30 days before contract acceptance (section 5-1.36E). Review of most action submittals is allowed 15 days, and a revised submittal the same number again (section 5-1.23B(1)). The specifications define a day as a calendar day. Caltrans Standard Specifications, 2026 Edition These are Caltrans contract terms. Other owners write their own, and a contract names the edition it uses.

Establishment periods

Caltrans counts plant establishment in working days. The specifications define a working day to exclude Saturdays and holidays, and their holiday table lists every Sunday, so the calendar length is longer than the number shown. In Type 1 establishment, the specified working days start after all work is complete, except establishment work and bid items that run until contract acceptance. In Type 2, they start after all planting work is complete, with the same exceptions, and the Department will not accept the contract unless establishment has been satisfactorily performed for at least the specified working days. Working days on which no work is required are credited. Working days on which the work is not adequately performed are not. Seasonal watering schedules are due within 10 days after the period starts, and a final inspection takes place 20 to 30 days before contract acceptance. Caltrans Standard Specifications, 2026 Edition, section 20-4

The number of working days is set per project: the definition refers to the number shown on the Notice to Bidders. The Construction Manual says Type 1 is typically used where highway planting is a major portion of the work and Type 2 where it is incidental to other work, which may continue during a Type 2 period. Caltrans Construction Manual, Section 4-20, October 2023 The manual page is dated October 2023 and predates the current specifications, so check it against them. Section 5-1.39C(2) of the specifications applies if a period of 3 years or more is shown on the Notice to Bidders. It changes who pays for some damage repair. We found no source for how often such a period is specified.

The City of San Diego’s Landscape Standards set maintenance periods in Section IV, the revegetation and erosion control guidelines, which cover manufactured slopes and other disturbed areas. Permanently irrigated slopes are maintained for no less than 90 days and nonpermanently irrigated areas for not less than 25 months. The period begins the first day after acceptance, and the City Manager may extend it. One other requirement bears on close-out. For development subject to the water budget section, a State-authorized professional certifies the installation by irrigation audit and submits it to the City before occupancy and use (section 2.7). San Diego Landscape Standards, April 2016 We read these sections only, so we cannot say whether the document sets a period for other planting. Check which edition is in force. Our article on tracking regulatory updates lists where the City publishes changes.

Working backward from a planting date

This example is our arithmetic on assumed dates. It uses three sourced figures: the City of San Diego’s 6-month average for advertise and award, its bid-protest delay of six months or more, and one nursery’s one to two years.

Assume a public design-bid-build project with planting set by the specifier for October of year 3. The month is assumed for the arithmetic and is not a recommendation. Assume six months of site work and irrigation before planting, and two months between award and the start of work.

Step Latest date Basis
Planting October, year 3 Assumed
Start of construction April, year 3 Six months of site work, assumed
Award February, year 3 Two months from award to start, assumed
Advertising, with documents through plan check August, year 2 City’s 6-month average
Nursery contact, if contract grown April, year 1 to April, year 2 Nursery’s one to two years, counted from the start of construction

A protest delay of six months would move award to August, the start to October, and planting to April of year 4. If the project holds to fall planting, the slip is a full year, to October of year 4. The establishment period then runs from planting, so acceptance is later again.

The nursery line raises a procurement question. Under design-bid-build the installing contractor is not under contract until award, eight months before planting here. Nursery contact one to two years before construction falls 10 to 22 months before award, so someone other than that contractor would have to make it, or the plant list would have to suit what can be supplied within the contract time. We found no public source that describes how owners arrange this. The Caltrans vendor statement cited above, by comparison, would be due in August of year 3.

What we could not settle

  • What review durations apply to landscape plan review in the City of San Diego? The City’s table has no landscape row.
  • What do Government Code sections 4216 and following, 65943 and 65950 say in their own text? The state legislative site did not open for us.
  • Which Permit Streamlining Act and CEQA time limits apply to a landscape-only permit?
  • What ticket life and renewal rule does DigAlert state for San Diego County?
  • Is there a published planting window by month for San Diego County?
  • What lead times apply to ordinary landscape nursery stock in Southern California?
  • How do public owners arrange contract growing before a construction contract is awarded?
  • How long do water-efficient landscape documentation, water meter and service orders, and seasonal work windows in environmental permits take? We opened no source on these.
  • How should several projects be scheduled together, and how would critical path and float change our breakdown? We did not open the Project Management Institute’s standards.

Using this in Field Method

Site Dossier assembles a source-linked public-data record for a point in San Diego County: terrain, sun and climate, soils, water, fire hazard mapping and planting zones, each with its source and date. That supports site analysis, the first phase above. It is not a survey, it shows no property lines, and it does not schedule work or track reviews.

Sources

  1. City of San Diego — Capital Improvements Program Timeline & Logistics Guidance Document (September 1, 2024)
  2. City of San Diego — Land Development Manual, Volume I, Chapter 1, Section 4: Development Permits/Approvals (October 2024)
  3. City of San Diego Development Services — Landscape Plan Review
  4. City of San Diego Development Services — Permit Processing Timeline
  5. California Department of Housing and Community Development — Housing Law Fact Sheet: Portions of the Permit Streamlining Act (April 2026)
  6. California Code of Regulations, Title 14, § 15105 — Public Review Period for a Draft EIR or a Proposed Negative Declaration or Mitigated Negative Declaration
  7. The Governor's Office of Planning and Research — CEQA 101
  8. DigAlert (Underground Service Alert of Southern California) — About DigAlert
  9. DigAlert (Underground Service Alert of Southern California) — FAQs
  10. USA North 811 — Field Guide, Northern California Edition (revised August 2026)
  11. UC Statewide IPM Program — Plant Properly
  12. Caltrans — Construction Manual, Section 4-20: Landscape (October 2023)
  13. California Botanic Garden — Restoration Nursery
  14. Caltrans — Standard Plans, Standard Specifications and Contract Item Codes
  15. Caltrans — Standard Specifications, 2026 Edition
  16. City of San Diego — Land Development Manual: Landscape Standards (revised April 2016)

These tools support site review and design studies. Read each tool’s stated capabilities and limits before use.

Explore Site Dossier
Back to Research