Transforming Southbank Boulevard

City of Melbourne with TCL and Mike Hewson · Melbourne, Australia

A Southbank boulevard rebuilt in stages to turn road space into public space favouring walking, cycling and transit. One stage has artist Mike Hewson’s play space of boulders on pinned-down dollies. A 2025 report listed stage six among overdue plans.

Recognised in 2024

The entry stands at the year of the award. An award records what a jury valued that year; it is not a measure of how the place performs or of lasting influence.

How it came about and changed

  1. 2010

    The Southbank Structure Plan raised the idea that the boulevard's median strip could become parkland.2

  2. 2017–2018

    Council adopted a concept plan in 2017. A June 2018 report described a staged project aiming at 2.5 hectares of new open space on Southbank Boulevard and Dodds Street. For stage 1 it listed early works from July 2018, removal of 39 trees and more than 65 new ones, with about 300 new trees planned across the whole project. June 2018 reports also described plans to remove traffic lanes, add 1.1 km of bike lanes and deliver a new accessible tram stop on Sturt Street. These were plans, not as-built checks.315

  3. 2018–2023

    Design of the Stage 5 play space, Rocks on Wheels, began in 2018. Artist and engineer Mike Hewson worked with the council’s design team, from the brief and boulder sourcing to the engineering of challenging elements. It has about two dozen large boulders and miniature wheels fixed to the ground. Dezeen describes boulders on what look like furniture dollies, with reinforced supports beneath. ASCE Civil Engineering reported that the boulders are anchored to the dollies, and that steel pins run through the wheels into a concrete slab. It reported soft rubber made to resemble bluestone paving, with real bluestone beneath the boulders. Because the boulders cannot be moved for maintenance, and the dollies can never be reached for replacement or refurbishment, it said they were designed for a long service life. This page found no maintenance or inspection schedule.4714

  4. 2020–2021

    In November 2020 Southbank News (now The Melburnian) reported that the original 2020 completion date had been missed, that three planned stages had become five, and that the project had been referred to the council’s audit risk committee. The report gave no outcome of that referral. The council attributed delay to third-party coordination, soil conditions and utilities; a long-term Southbank resident, David Hamilton, rejected blaming third parties. In November 2021 the same paper reported that the 2020–21 annual report of the council’s audit and risk committee cited “significant cost overruns in excess of $8 million”; the article did not mention the 2020 referral. It also reported the committee report as saying management had already significantly improved its major project management framework, and had accepted and implemented further improvements identified by an internal audit. Lord Mayor Sally Capp conceded that the project had taken far longer than expected.216

  5. 2022

    The play space opened on 7 November 2022. It was designed to look risky. ABC reported mixed reactions from listeners: one, who had visited with another family, said the children thoroughly enjoyed it; another worried that it could give children false confidence in places that are dangerous. Southbank News quoted two residents’ group presidents. David Hamilton objected to so many large rocks in a small space, but also noted how well children had received it. Tony Penna said he thought it had achieved its purpose as a functional children’s park, and that the design was never discussed in community consultation. The Lord Mayor said it was a very safe place to play, that experts had tested the equipment and that the platforms were set firmly into the ground with steel rods. The ABC report mentions no injuries.56

  6. 2022

    Southbank News (now The Melburnian) reported 22,000 m² of new public open space and 400 trees. Stage six, between City Road and Southbank Promenade, was unbuilt. The report said Southbank News understood that its funding and construction depended on a neighbouring private tower development then due in 2028.6

  7. 2023

    Dezeen reported the council’s account: the project team tested the design and build, and playspace auditor DMC Design signed it off. ASCE Civil Engineering reported that boulder spacing was set to meet fall-zone and other safety requirements of Australian Standard 4685, Part 1, and that the playground had to pass a safety inspection before opening. This page has seen no audit or inspection report. The same year AILA gave the project state and national awards. The national jury valued the reuse of redundant road infrastructure, the pairing of art and play, and planting drawn from local ecologies. Its comments on climate resilience and urban heat are not measurements.714138

  8. 2024

    TCL, one of the recipients, lists a WLA Awards Award of Excellence, Built - Urban Design. This page found that honour only on TCL’s own pages. The Australian Urban Design Awards, announced on 18 March and reported independently, gave the project the award for built projects at local and neighbourhood scale.1129

  9. 2024–2026

    A July 2024 report in The Melburnian said the council had previously indicated that completing stage six partly depended on Beulah’s STH BNK project, the tower named in 2022, although the developer was understood to have made clear to the council that it should not hold up delivering its street upgrades. The report said the council had pledged $250,000 for stage six in that year’s budget. In March 2025 the paper reported that BSSPV Pty Ltd, the company managing STH BNK, had been placed into voluntary administration on 11 February, and named stage six among overdue plans for which the site was a “major missing link”. A Beulah director referred to pursuing “an alternative strategy to realise the STH BNK project”. In May 2026 it reported that the site was heading to market and that receivers had been appointed to two Southbank sites late in 2025. Beulah said the sale campaign did not preclude the project proceeding. The 2026 article does not mention stage six. In a search on 25 November 2026, this page found no later council statement than the one reported in 2024 on how or when stage six will be funded; the council’s website was not opened.171819

  10. 2026

    In June 2026 a report said a parent’s video questioning whether the play space was safe for a two-year-old had renewed debate. Some commenters shared the concern, one calling it very dangerous for toddlers; others defended risky play as important for child development. The acting Lord Mayor, Roshena Campbell, said “every element is firmly secured and thoroughly tested in consultation with child safety experts”. Hewson said there was nothing risky about his playgrounds because they are fully compliant, and that the Southbank layout was planned to keep objects out of the running zone. The report mentioned no formal review of the play space.11

Approvals and legal steps

  • 2017 Council adopted the concept plan for Southbank Boulevard and Dodds Street.3

No council minutes, permits or state transport approvals were opened. The month of adoption was not confirmed from a record. The play audit sign-off is reported in the record above and is not listed as an approval.

Funding

  • 2016 Southbank News (now The Melburnian) later reported that the council announced the project at a cost of $15.9 million. This was an estimate.2
  • 2017 The estimate was revised to $34 million, as reported in 2020.2
  • 2020 The council confirmed to Southbank News a revised total forecast of $47 million (reported 11 November 2020).2
  • 2022 Southbank News (now The Melburnian) and, in January 2023, Dezeen put the Southbank public space upgrade at $44 million. Neither is a final audited account.67
  • 2023 Dezeen gave $2.4 million for the Rocks on Wheels play space (reported January 2023).7

These are press-reported estimates and forecasts in dollars, taken to be Australian. No official final cost or funding split was opened. Their scopes may differ, including how Dodds Street is treated, so they should not be subtracted or read as one series. The 2022 report tied stage six funding to the private tower, as an understanding only, so the $44 million should not be read as covering that stage. This page opened no developer agreement.

People

  • City of Melbourne (City Design) Client; landscape architecture (Stages 1–5), urban and industrial design
  • TCL Landscape architects with City Design (Stages 1–4)
  • Mike Hewson Artist; Stage 5 play space with City Design, including engineering of challenging elements
  • Paul Thompson Plant designer
  • Wurundjeri Woi-wurrung Cultural Heritage Aboriginal Corporation, Bunurong Land Council, Boon Wurrung Foundation First Nations cultural collaborators
  • Play DMC Play auditor
  • Event Engineering Stage 5 engineer (AILA credits); structural designer (ASCE)
  • Felicetti Stage 5 structural engineer (AILA credits); foundation design (ASCE)
  • Tonkin Taylor Stage 5 geotechnical and geological engineering
  • Cardno (now Stantec) Civil, traffic and services
  • 2Construct Contractor, Stages 1–2
  • Multipro Civil Construction Contractor, Stages 3–5
  • Light Rail Consultants Tram infrastructure design
  • GHD Traffic modelling
  • Ten Buuren Irrigation Designs Irrigation design
  • Webb Australia Group Electrical engineering and lighting design
  • Citywide Service Solutions Tree removal and planting

Sources for this page

  1. TCL, Southbank Boulevard (project page)
  2. Southbank News (now The Melburnian), Southbank Boulevard: the failed anatomy of Melbourne’s most expensive park (11 November 2020)
  3. Apartments.com.au, Stage 1 of Transforming Southbank Boulevard and Dodds Street commencing this month (21 June 2018), by Laurence Dragomir
  4. Landscape Australia, Discovery and daring: Rocks on Wheels (19 March 2023), by Bede Brennan
  5. ABC News, Risk play park in Melbourne CBD designed to look perilous, but mayor says it is very safe (7 November 2022)
  6. Southbank News (now The Melburnian), Southbank Boulevard reaches an end, but new playground splits opinion (9 November 2022)
  7. Dezeen, Mike Hewson installs giant boulders on wheels for risk play space (4 January 2023)
  8. Landscape Australia, 2023 National Landscape Architecture Awards: Award of Excellence for Civic Landscape (20 October 2023)
  9. Landscape Australia, Winners revealed: 2024 Australian Urban Design Awards (19 March 2024)
  10. TCL, TCL wins top awards at 2024 Australian Urban Design Awards (19 March 2024)
  11. NZ Herald, Kids’ playground designed by New Zealander terrifies parents in Melbourne (22 June 2026; from news.com.au)
  12. TCL, TCL awards list
  13. Landscape Australia, Winners announced: 2023 Victorian Landscape Architecture Awards (18 July 2023)
  14. ASCE Civil Engineering, ‘Risk play park’ requires innovative engineering in Australia (April 2023), by Jay Landers
  15. Bicycle Network, Southbank Boulevard project gets rolling (21 June 2018)
  16. The Melburnian, Southbank Boulevard’s $8m blowout for city’s most expensive park (10 November 2021)
  17. The Melburnian, “Southbank in limbo”: concern as major developments stall (3 July 2024)
  18. The Melburnian, Where to, now? Major blow for Beulah’s Southbank vision (5 March 2025)
  19. The Melburnian, STH BNK site heads to market in major blow for Beulah’s stalled Southbank supertower (13 May 2026)

Researched on 2026-11-25 from the sources listed; a fact that could not be confirmed in a source was left out. Pictures are public domain or under an open licence, credited as their file page asks.

The question it brings · interpretation

What before-and-after measures would show whether reclaimed road space supports habitat, keeps people and trams moving, and invites play?

Each question is Field Method’s interpretation, not a claim made by the source.

The date

2024: WLA Awards Award of Excellence, Built - Urban Design, as listed by TCL, one of the recipients; not independently confirmed. The year of this entry is the award year. Plan: adopted by Council in 2017. Construction: staged works from 2018. The Stage 5 play space opened in November 2022; a stage six was then still unbuilt.