ProjectEcology and land

2023

The Dark Line

mICHELE&mIQUEL and dA VISION DESIGN, for New Taipei City · Ruifang and Shuangxi, New Taipei, Taiwan

A disused rail route through two old tunnels became a walking and cycling path on raised rebar decking, described as leaving old ground unbroken. LILA also says hidden lighting spares the vaults where bats roost.

Recognised in 2023

The entry stands at the year of the award. An award records what a jury valued that year; it is not a measure of how the place performs or of lasting influence.

How it came about and changed

  1. 1922–1985

    A city tourism release dates the old Sandiaoling tunnel's opening to 1922 and says it carried coal trains and later the Yilan Line. The city's account in a Control Yuan report says the Sandiaoling and Sanguazi tunnels were retired and sealed in 1985, after Yilan Line widening works finished in 1984.72

  2. 2012–2018

    The Control Yuan report says a 2012 city road feasibility study advised, given legal use limits tied to the tunnel structure, repairing it as a bikeway. A later consultancy plan supported a bid for national cycling-route money. LILA says a 2018 design competition covered the Mudan to Sandiaoling section, and mentions a connection to be devised to replace a bridge washed away by floods.21

  3. 2019–2020

    LILA credits mICHELE&mIQUEL and dA VISION DESIGN and dates design to 2019–2020. The city told investigators that the design contractor, not named in the text read, proposed a fully raised, open deck instead of large-scale grading and a hard base, to reduce built surfaces and human disturbance, with indirect lighting that brightens on sensing people. It described tunnels disused for decades, with sand and rock, water-cut marks, stalactites and bats.12

  4. 2019

    The city told investigators it designated tunnel heritage as a municipal historic building in 2019. The passage notes surviving tunnel portals, inscriptions and masonry but does not set out which structures the designation covers.2

  5. 2019–2022

    A city results page dates phase one, a rest station at the south entrance, from 16 September 2019 to May 2020, and phase two, the main route, from 6 March 2020 to March 2022. A works page agrees on phase two. The Control Yuan report gives completion on 1 March 2022 and acceptance inspection on 30 November 2022. The basis for the public trial between those dates was not found; no conclusion is drawn.452

  6. Design account

    LILA's text describes one repeated material, reinforcing bar, bent into railings, seats, bicycle racks and markers. It says the decking at the start of the route is raised to leave the old ground unbroken, and that in the tunnel two metal beams, which support rebar grating panels, build new rails above ground left untouched. Separately, it says a hidden light source spares the tunnel vault, where bat colonies hang. It describes a footbridge on the gorge wall, with concrete masses set against the cliff and metal brackets craned from the road, plus a light well and a reflecting pool. These are descriptions, not measured effects.1

  7. 2022

    The city announced a trial from 3 July to 3 September 2022, with capped, booked entry and a section where bicycles had to be pushed. Its release said seepage from the tunnel walls forms a mirror pool. City pages date official operation to October 2022.645

  8. 2022

    The Control Yuan report says some groups (cyclists) criticised the route as very poorly suited to cycling. It says that, because outside criticism was so strong, the city took the view that the tunnel was not only for cycling or walking but also for environmental sustainability, and stressed the history and ecology it preserves. After a meeting on 28 July 2022, the name changed to an eco-friendly tunnel, publicity shifted away from the bikeway, and rules were posted, including a 10 km/h cycling limit and push sections.2

  9. Through travel

    The report says full booking, opening from 08:30 to 16:30 and a Tuesday closure mean riders without a booking, or outside open times, cannot pass through. The Transport Research Institute found nearby hilly, winding roads hard to use as an alternative and suggested linking Shuangxi and Houtong stations by rail with bikes. The report says that approach greatly reduces the approved plan's transport link between Sandiaoling and Mudan.2

  10. 2022–2025

    The city told investigators that early trial operation under the Shuangxi District Office allowed 320 entries a day. The tourism department took over on 1 January 2023. A trial without weekday booking brought crowds beyond environmental capacity, bunching and walkers and cyclists getting in each other's way. From 29 August 2023 booking applied daily: eight slots of 160, up to 1,280 a day. The weekly closure moved from Monday to Tuesday on 1 August 2025. PTS reported in October 2023 that the 29 August change was made to reduce the impact. No ecological data behind either cap was found.29

  11. 2023

    On 30 October 2023 the public broadcaster PTS reported that designer Wu Chung-hsun had recently found fewer leaf-nosed bats roosting in the tunnel, at times only 10-odd. PTS said the tunnel once had more than 50 Formosan leaf-nosed bats and that after it opened to visitors the number at one point fell to just over 10. It quoted Wu as saying that with care during construction there were at least 50, and that human disturbance was now worse than then. Metalocus names a Chung-Hsun Wu as founder of dA VISION DESIGN. PTS said the city had monitored since January 2023 but did not yet have enough data to analyse why the bats had declined. It reported new signs at both entrances and quoted a city tourism official as saying that visitors can speak softly or slow down. The PTS passages read give no counting method. These accounts do not establish a cause.910

  12. 2025

    The Control Yuan inquired into a complaint alleging unsafe design of the route surface (the rebar grating, and insufficient lighting in the tunnel), disordered management and a mismatch with the grant's purpose. It made a site visit on 30 September and questioned city staff on 29 October. The deck is a grating of 16 mm ribbed bar at a stated 2.4 cm spacing; the report does not say whether that is the clear opening.2

  13. Paving context

    The report quotes an urban road design code on accessible routes: avoid drainage grates or covers; if unavoidable, set grates across travel, with the opening's short side preferably under 1.3 cm. It says the Transport Research Institute's 2017 bikeway manual is similar; the institute states this for drainage grates, as clear bar spacing. The 2018 grant letter asked the city to refer to the manual and road code. A 2018 Education Ministry letter said grant reviews considered suitability for women, older people and people with disabilities.2

  14. Agency views

    The Interior Ministry said the road design code does not apply because this is not a road it governs. It suggested, for safety, reviewing controls on cycling, given the grating or low-energy lighting. The Sports Ministry called the manual a reference, which grant cases had been asked to consult in design, and held that the project did not breach the grant's cycling purpose or depart from its core aim.2

  15. City account

    The city said it consulted the manual and road code, adapting them for a leisure route that is not a municipal road. It said bar spacing followed repeated tests with rental-bike tyres, gaps run across travel, flat bars below mean turning tyres will not sink, and normal use is no problem. It said a visit by the grant programme's advisory team confirmed friendly, barrier-free bikeway conditions. It reported closer bars at some stopping places and reflective strips on bike racks. Lamps reach full level when people pass, then keep basic edge light; night opening is not allowed in principle.2

  16. Injury figures

    City statistics in the report, for 1 January 2023 to 31 July 2025: injured walkers equal 0.0128% of all visitors; injured cyclists equal 0.038% of those entering by bicycle. The bases differ. The city cites 428,373 total visitors and calls the ratios very low. A footnote, to 31 July 2025, gives 55,153 bicycle entries and 21 bicycle injury cases. No walker injury count, injury definition or severity is given. The figures were not checked here.2

  17. 2025

    On 17 October 2025, in a release noting a 2025 National Excellence in Construction Award (Excellence Prize, best management and maintenance category), the city tourism department reported that, after about two and a half years of ecological monitoring, bat activity was seen at both ends and deep inside. It said this showed an important core area for stable bat habitation, that the number and variety of nearby species had risen slightly, and that this signalled human impact was under control. It gave no method, counts or baseline, so these claims, including any project effect, cannot be assessed. It also mentions low-brightness lamps and drainage-channel flow blocks whose small drops form cascades.7

  18. Opinion 1

    Control Yuan investigation opinion on the complaint; the report text read is undated and follows the 29 October 2025 questioning. After a site visit, it found the matter a gap between public-policy ideal and practice: by reusing the old tunnels, the city created a leisure cycling route suited to different groups while caring for local ecology, and did not depart from the grant programme's core aim. This opinion was to be sent in reply to the complainant.2

  19. Opinion 2

    A separate opinion in the same undated report found that, in a design that had to weigh heritage, ecology, transport, tourism and other matters, the transport function was greatly reduced and its character as landscape installation art more prominent. It noted awards and sharply divided views, citing a mismatch between the application name and current operation and publicity, and injuries in bicycle falls. It asked the city to review, improve and reply, and went to the Sports Ministry for reference in future approvals.2

  20. 2026

    A Control Yuan closed-case table records the city's handling: it had repositioned and renamed the site, with booked entry, a 10 km/h cycling limit and push sections; it made cyclist falls a priority for continuing site safety management; and it would add combined checks across planning, design and operation for similar future projects. On 12 February 2026 the Education and Culture Committee closed the improvement request and the investigation. The table does not mention paving changes. Closure is not a measured safety result.3

  21. Visitor status

    The city visitor page, updated 27 January 2026 and read on 25 November 2026, lists hours of 8:30 to 16:30 (last entry 16:00), Tuesday closure with a holiday exception, closure when work or school suspension is announced, and advance booking. Riders must turn on headlights; without a lamp, the bicycle must be pushed the whole way and not ridden. Bicycles must also be pushed both ways between Sanguazi tunnel and the wall-hung walkway. It bars slippers and high heels on the open grating and flash or torches aimed at animals. It gives a total length of 3.19 km for the eco-friendly tunnel. It is not a live notice.8

Approvals and legal steps

  • 2018 On 4 December 2018 the national Sports Administration approved the bikeway plan, with a total of NT$99,797,634 and a grant of up to NT$59.8 million.2

The city told investigators that experts, the Sports Administration, the railway administration and city units reviewed the design before approval, with no dates in that passage. It also said the route mostly lies on slopeland conservation land outside urban plans, and that tunnel and land fall under Taiwan Railway Corporation asset management. No land-use, slope, tunnel safety or ecological permit documents were found.

Funding

  • 2018 Approved plan of 4 December 2018: total NT$99,797,634, with a national grant capped at NT$59.8 million under a forward-looking infrastructure cycling programme. The city was to cover costs above the grant.2
  • 2019–2020 Contract awards: NT$17,951,129 for design and supervision (8 March 2019) and NT$179,266,000 for construction (22 January 2020). These are award prices, not final costs.2
  • 2022 In the city's release of 2 July 2022, Mayor Hou Yu-ih gave a total budget of NT$310 million, stated alongside the old tunnel's length of about 3.19 km. The passage does not itemise what the figure covers.6
  • Final account The Control Yuan report gives a settled project works cost of over NT$260 million, after added route length, tunnel and slope protection, emergency slope hazard works and price adjustments. No settlement date is given.2

The sources do not reconcile the 2022 budget of NT$310 million with the settled works cost of over NT$260 million, or say whether either includes the phase-one rest station. Final national and city shares and operating costs were not found.

People

  • mICHELE&mIQUEL Design
  • dA VISION DESIGN Design
  • ARTEC 3 STUDIO Lighting
  • YU SHENG Engineering Consultants and Elements Structural Engineering Associates Structural engineering
  • GEOLITHE Engineering Geotechnical engineering
  • SINOTECH Engineering Consultants Tunnel structural consultant
  • YUAN DIAN Engineering Consultant Electrical engineering
  • DAO TIAN Construction Builder
  • Public Works Department, New Taipei City Government Client, as credited by LILA
  • Taiwan Railway Corporation Asset manager of tunnels and land, per the city
  • New Construction Office, New Taipei City Government Procuring office for design, supervision and works
  • Shuangxi District Office Early trial operation
  • Tourism and Travel Department, New Taipei City Government Operator from 2023, using a commissioned firm not named in the report
  • Two consultancies, names masked in the report Joint holders of the design and supervision contract

Sources for this page

  1. Landezine International Landscape Award, The Dark Line (LILA 2023 Project of the Year)
  2. Control Yuan, Taiwan, Control Yuan investigation report on the Sandiaoling tunnel bikeway (Chinese)
  3. Control Yuan, Taiwan, Control Yuan committee table of closed investigation cases, case 114教調31 (Chinese)
  4. New Taipei City Government, Sandiaoling eco-friendly tunnel, city results page (Chinese)
  5. New Construction Office, New Taipei City Government, Sandiaoling eco-friendly tunnel new construction project (Chinese)
  6. New Taipei City Government, Release on the mayor’s ride along the route, 2 July 2022 (Chinese)
  7. New Taipei City Tourism and Travel Department, City tourism release on the tunnel and its 2025 award, 17 October 2025 (Chinese)
  8. New Taipei City Tourism and Travel Department, Sandiaoling eco-friendly tunnel, visitor page (Chinese)
  9. PTS News (Public Television Service, Taiwan), 三貂嶺生態隧道開放觀光 葉鼻蝠銳減一度剩10幾隻 (30 October 2023, Chinese)
  10. Metalocus, The Dark Line by Michèle & Miquel and da VISION DESIGN (18 May 2023)

Researched on 2026-11-25 from the sources listed; a fact that could not be confirmed in a source was left out. Pictures are public domain or under an open licence, credited as their file page asks.

The question it brings · interpretation

What records from before works, during construction and after opening would separate the effects of building, lighting and visitors on the bats?

Each question is Field Method’s interpretation, not a claim made by the source.

The date

2023: LILA 2023 Project of the Year; the year of this entry is the award year. Design 2019–2020 and completion 2022 (LILA). City sources: works from September 2019 to March 2022, public trial from 3 July 2022.

Checked against

See it on the timeline