ProjectWater, climate and policy

2020

Phase Shifts Park

Mosbach Paysagistes, with Philippe Rahm architectes and Ricky Liu & Associates, for Taichung City Government · Xitun District, Taichung, Taiwan

A 67-hectare former-airport park designed around mapped heat, humidity and pollution, with devices meant to cool, dry or reduce pollution. Which devices exist or run is not established.

Recognised in 2020

The entry stands at the year of the award. An award records what a jury valued that year; it is not a measure of how the place performs or of lasting influence.

How it came about and changed

  1. 2011

    The city announced the international competition result in October 2011. Its report says 58 entries from 22 countries arrived in the first stage and refers to four shortlisted teams. It places facilities by heat, humidity and pollution indices and plans 250 ecological regulators. It records the deputy mayor saying these must be passive, adding no carbon emissions or electricity use.2

  2. Design

    Design aim: keep and strengthen differences in conditions, making naturally cooler, drier and cleaner areas more so. Three computational fluid dynamics simulations informed three climate maps. Devices were designed to cool, dry or reduce pollution. These are design studies, not results from the built park.534

  3. After a change of administration (essay's 2013–2016 section)

    Alessandro Martinelli, in an April 2026 essay, writes that after a change of political leadership the incoming administration revised the design, and that construction of the cooling systems and related facilities was halted although some had already been built. A new mayor set up a tree committee, which favoured native species over large exotic trees. The essay calls the proposed ground cooling system the most contested element, criticised by environmentalists as wasting energy. It cites a National Audit Office report (dated 2021 in its references, 2022 in its text) for about NT$50 million in cancellation fees paid to contractors; that report was not read. The essay places this under a 2013–2016 design-development heading but gives no exact date or stated reason for the halt and names no mayor or decision. No official record of the halt was read.12

  4. 2017

    The city announced plans for 91 simple sensor poles, for readings such as temperature, humidity and wind, and 30 multi-function poles adding pollutants and noise. Testing was due by the end of 2017. The award page's project text describes real-time readings on a phone app. No source read establishes that the app or sensor network worked after opening.61

  5. 2018

    On 4 September the city said five detention ponds, with a stated total of 180,755 tonnes against 177,500 required under the Shuinan district drainage plan, had come through heavy rain in late August. It also described ultrasonic water-level gauges and broadcasts to move visitors to safety above a set level. It gave no rainfall or level readings; later operation was not established. A 1 November release announced trial opening from 3 November.78

  6. 2020

    The opening ceremony was on 6 December. The city described a 67-hectare park with 12 sensory facilities, smart streetlights and sensors, solar panels, five detention ponds and a reclaimed-water system. It reported over 1,000 existing trees kept, over 10,000 native trees added and a planned native share of 83%. Martinelli, writing in 2026, says many publicised sensory installations were not ready or working at opening, planned high-tech climate devices were absent and planting was mostly young. The essay does not match its installations to the city's 12.912

  7. 2020–2021

    Martinelli, writing in 2026, reports complaints after opening about heat, little shade, uneven paving, poor restrooms and minimal barriers at water features. The essay gives no measured temperatures. These are not reports of present conditions.12

  8. 2021

    In February the Construction Bureau, answering councillors who criticised bare ground, said stabilised soil had been planned alongside lawn partly for cost, and that it lets water through; the report cites no test. In November Liberty Times reported councillors' complaints of lifting paving, worn restrooms and idle experience zones. The bureau said improvements were being planned.1310

  9. 2022

    On 14 September Minzhong Daily, via Yahoo News, reported Councillor Li Zhong (李中) saying that the operable mist and fan system had its installation arbitrarily halted (中止施作) by a former director (前局長), whom the item names without giving the bureau, so that the park could not deliver its cooling performance, and that the city had to pay the contractor more than NT$50 million in compensation. Li also said the leftover microclimate plant room, worth over NT$60 million, now only stores clutter, and criticised a change to smaller trees. These are the councillor's claims. The mayor answered that improvements would continue and trees would be added if too few. No response on the cooling or money claims from the former director or the city was found, and no official record of the halt was read. The item does not establish that these are the works Martinelli describes.11

  10. 2025

    As of 2025, Martinelli writes, shade sails and more trees had been added, pavilions had been offered to private operators and regular events were held. No source read says whether the water-feature barriers changed.12

Approvals and legal steps

No planning, building or environmental approval was read in an opened source. A competition result and an opening are not approvals.

Funding

  • 2011 City report at the competition result: Central Park cost of more than NT$2.7 billion, for a site then given as about 68 ha. A figure at design stage, not a final account.2
  • 2021 Liberty Times, 23 November: the Construction Bureau put maintenance at about NT$58 million a year and mentioned another NT$20–30 million for small works that year. Not construction funding.10
  • 2026 account Martinelli's April 2026 essay gives an initial planning and construction budget of NT$2.7–3.4 billion. No official budget record or final account was read to confirm it.12

No final account or funding shares were read. These figures differ in date and scope and should not be added. The NT$50 million cancellation fee (essay, citing an unread audit report) and the over NT$50 million compensation and NT$60 million plant room (one councillor, 2022) are claims reported in the evolution items, not confirmed by an opened official record.

People

  • Mosbach Paysagistes (Catherine Mosbach) Landscape architect; entered the award as lead
  • Philippe Rahm architectes Co-designer
  • Ricky Liu & Associates Architects and Planners Co-designer; local architect (Martinelli)
  • Transsolar Climate engineering: device design input, wind and device simulations, annual comfort modelling
  • Bollinger+Grohmann Structural engineering, preliminary and detailed design
  • Patrick Rimoux Lighting (Transsolar credit)
  • Taichung City Government Client; its Construction Bureau answered on upkeep

Sources for this page

  1. Landezine International Landscape Award, Phase Shifts Park
  2. Taichung City Government, Central Park report to municipal meeting (Chinese), 17 October 2011
  3. Bollinger+Grohmann, Jade Eco Park
  4. Transsolar, Central Park Masterplan, Taichung
  5. Landscape Australia, Designing for climate change (Walliss and Toh, 2016)
  6. Taichung City Government, Three types of smart poles for Central Park (Chinese), 18 October 2017
  7. Taichung City Government, Five detention ponds and August rains (Chinese), 4 September 2018
  8. Taichung City Government, Trial operation from 3 November (Chinese), 1 November 2018
  9. Taichung City Government, Central Park opens (Chinese), 6 December 2020
  10. Liberty Times, One year on: councillors on damage and idle zones (Chinese), 23 November 2021
  11. Minzhong Daily via Yahoo News, Councillor on smaller trees and a halted mist and fan system (Chinese), 14 September 2022
  12. Landezine, Will It Pass or Not? Taichung Central Park (Alessandro Martinelli, 2 April 2026)
  13. Liberty Times, Councillors on bare ground; bureau reply (Chinese), 3 February 2021

Researched on 2026-11-25 from the sources listed; a fact that could not be confirmed in a source was left out. Pictures are public domain or under an open licence, credited as their file page asks.

The question it brings · interpretation

What paired measurements in places mapped as cooler and warmer, with any built devices on and off and as trees grow, would test a park's microclimate promise?

Each question is Field Method’s interpretation, not a claim made by the source.

The date

2020: LILA award year. Competition result announced October 2011; trial opening from 3 November 2018; opening ceremony 6 December 2020 (Taichung City Government).